葛洲坝水电站增容改造中机组拆除及蜗壳加固研究

Translated title of the contribution: Study on unit disassembly and spiral case reinforcement during capacity-increasing improvement for Gezhouba Hydropower Station

Research output: Contribution to journal › Article › peer-review

Abstract

Three dimensional FEM is adopted to analyze the stress and deformation of spiral case of Gezhouba Hydropower Station under the statuses : before the capacity-increasing improvement ; during the disassembly of the spiral case ; after the capacity-increasing improvement. Based on the calculation, the reinforcement scheme for the spiral case is proposed, and then the FEM calculation is also made on the scheme. Through the comparative analysis on the phase Ⅱ concrete for the cone section under the three statuses mentioned above, it shows that not only the unit disassembly scheme is feasible, but the reinforcement design is also effective.
Translated title of the contributionStudy on unit disassembly and spiral case reinforcement during capacity-increasing improvement for Gezhouba Hydropower Station
Original languageChinese
Pages (from-to)56-59
Number of pages4
JournalWater Resources and Hydropower Engineering
Issue number2
StatePublished - 1 Feb 2010

Indexed by

  • CSCD

Fingerprint

Dive into the research topics of 'Study on unit disassembly and spiral case reinforcement during capacity-increasing improvement for Gezhouba Hydropower Station'. Together they form a unique fingerprint.

Cite this