Abstract
We consider the problem of two-machine flow-shop scheduling with a single server and unit server times, we show that this problem is NP-hard in the strong sense and present a simple greedy algorithm for it with worst-case bound 3/2.
| Original language | English |
|---|---|
| Pages (from-to) | 123-127 |
| Number of pages | 5 |
| Journal | JOURNAL OF INFORMATICS AND MATHEMATICAL SCIENCES |
| Volume | 4 |
| Issue number | 1 |
| State | Published - Jan 2012 |
Keywords
- Two-machine
- Flow-shop
- Single server
- Complexity
- NP-hardness
- Worst-case analysis