摘要
To ensure the safety of substation expanding and new shunt reactor operation, we researched the overvoltage of shunt reactor during switching-on process by theoretical analysis, tests and simulations, and theoretically analyzed the reasons of the overvoltage from two aspects, namely, mechanism of transient prebreakdown of SF6 breaker and reflection and refraction of wave. Moreover, we established a SF6 breaker prebreakdown model in ATP-EMTP to simulate the field tests. Tests and simulation results showed that the specific overvoltage on the reactor during process of switching-on could reach 4.0. However, simulation results showed that, with resistance and capacitance absorption equipment, the specific overvoltage could be decreased to 1.68 in the same condition. Simulation results indicated that the absorption equipment could be an effective measure for overvoltage limitation, which not only decreased the systematic overvoltage but also restrained systematic harmonics. The pre-breakdown phenomenon introduced in this paper could be referred for protection of shunt reactor operation in substations.
| 投稿的翻译标题 | Overvoltage of shunt reactor caused by prebreakdown of SF6 breaker and protection measures |
|---|---|
| 源语言 | 中文 |
| 页(从-至) | 75-80 |
| 页数 | 6 |
| 期刊 | Gaodianya Jishu/High Voltage Engineering |
| 卷 | 39 |
| 期 | 1 |
| DOI | |
| 出版状态 | 已出版 - 1月 2013 |
关键词
- Capacitance
收录
- EI
- Scopus
学术指纹
探究 'Overvoltage of shunt reactor caused by prebreakdown of SF6 breaker and protection measures' 的科研主题。它们共同构成独一无二的学术指纹。引用此
- APA
- Author
- BIBTEX
- Harvard
- Standard
- RIS
- Vancouver